Temporary site power is either planned properly once or paid for every day: an undersized unit stalls the crane, an oversized one burns diesel for nothing. These are the steps our technicians use when quoting Riyadh sites.
1. List the loads by phase
Loads change as the project moves. Start with a simple table:
| Phase | Typical loads (approx. running power) |
|---|---|
| Mobilisation | Site office with AC and lights ≈ 3.5 kW each; labour accommodation; security lighting |
| Excavation | Dewatering pump ≈ 5.5 kW each; air compressor ≈ 7.5 kW |
| Structure | Tower crane ≈ 45 kW; concrete mixer ≈ 5.5 kW; welder ≈ 8 kW; rebar bender ≈ 4 kW |
| Finishing | Power tools, temporary lighting, cooling finished floors |
Approximate values from our load calculator; use your equipment’s data plates where you have them.
2. Allow for motor starting current
Motors started direct-on-line draw several times their running current at start-up. So adding up kilowatts is not enough: the generator must survive the largest motor starting while it carries everything else. Soft starters and variable-frequency drives cut that surge sharply.
3. Split the critical loads
- A dedicated unit for the tower crane — do not share it with welders
- A unit for offices and accommodation so they ride through site load swings
- Self-powered light towers for night work
4. Size for 50–80% typical load
Diesel generators run most efficiently at medium-to-high load. Leave headroom for growth and motor starts, but do not oversize.
5. Plan distribution and safety
A temporary distribution board, correctly sized cables, earthing and residual-current protection — installed under a qualified electrician. Cables and a distribution board can be added to the rental quotation, subject to availability.
6. Budget diesel and the permanent-connection date
Use the diesel consumption table to budget fuel, and plan early for the period before the permanent connection so commissioning and handover are not delayed.
Contractor questions
Should I use one big generator or several smaller ones?
On most sites it is better to split loads: a dedicated unit for the tower crane and another for offices and accommodation. That reduces voltage dips and stops one fault from shutting the whole site.
How much diesel will site generators use?
Roughly 0.27 L per kWh at 75% load. A 250 kVA unit uses about 40 L per hour — around 400 L for a 10-hour shift.
Is running a generator at very low load harmful?
Over time, yes. Long periods below about 30% load cause unburnt fuel to build up in the exhaust (“wet stacking”). That is another reason not to oversize.
General guidance, not an electrical design. The final size is confirmed by our technician against your equipment list.