One of the most common causes of late handover: the building is nearly ready, but the permanent supply from the Saudi Electricity Company is not yet energised. Without power, lifts, pumps and HVAC cannot be tested and handover cannot start. A temporary generator bridges the gap.
What needs power before the connection?
| Activity | Loads | Usual approach |
|---|---|---|
| Testing & commissioning | Lifts, pumps, HVAC units, fire systems | Staged, system by system |
| Snagging & finishing | Lighting, power tools, partial cooling | A steady mid-size unit |
| Early handover & sales | Show units and common services | A quiet canopy unit |
How to size it
- Add up the largest systems that will be tested at the same time
- Allow for the starting current of the largest motor (lift or pump)
- Leave margin for ongoing finishing work
- Check with the calculator: building tab
Plan early
Build the generator into the handover programme rather than waiting for the problem. Monthly rental suits this stage because the connection date can move, and it extends easily.
Note: standby requirements for fire and life-safety systems are set by the Saudi Building Code, Civil Defense requirements and your project consultant.
Common questions
Do I need a generator sized for the whole building?
Usually not. Commissioning happens in stages, so a unit sized for the largest system under test plus its companions is often enough.
Who connects the generator to the building’s boards?
A qualified electrician from the contractor or owner, through a suitable connection point and changeover. We supply, start and maintain the generator.
And after the permanent connection?
We collect the temporary unit, and can supply a permanent standby generator for lifts, pumps and common services. Generators for sale